Horizontal Fan Coil Unit Project Guide: From Drawings to Handover

A horizontal fan coil unit is a room-side terminal in an HVAC system, often installed above a suspended ceiling where a “low profile” or “low-profile cabinet” label does not by itself prove installation fit. A workable horizontal fan coil unit project also proves the air duty, water pipe circuit, drain route, control sequence and service-removal path. Beyond that, it needs a proven ventilation boundary and acceptance records. This manual illustrates these requirements as they appear in the design basis, as well as throughout the process of ceiling coordination, commissioning, handover, and the replacement survey.

Project rule: treat the fan coil, ceiling, ducts, pipes, drain, power and controls as one interface package. The selected-unit instructions, adopted code and project specification remain the acceptance authorities.

Use this guide to answer five handoff questions

  1. What must be fixed before design release?
  2. Can every service item move through the finished ceiling?
  3. Which trade owns each air, water, drain and control interface?
  4. What evidence permits ceiling closure and final acceptance?
  5. When is a replacement truly reusable, adaptable or a redesign?

What Changes When a Horizontal Fan Coil Is Installed Above a Ceiling?

What Changes When a Horizontal Fan Coil Is Installed Above a Ceiling? — Koven Air

Moving the service line out of the occupied space does not remove the service problem; the horizontal unit still needs an access route in place. The filter still needs to be able to slide out. The motor or blower assembly still needs a removal route. Valves, strainers, vents, electrical terminals and the drain connection must remain reachable after the grid, lights, sprinklers and cable trays are installed.

This distinction differentiates this field manual from product catalogs. If you want current product models, factory options or engineering data, please visit the horizontal fan coil unit model page. If you’re comparing how horizontal fan coil units work in a hotel, residential building or another indoor climate control application, the fan coil types and operating basics belong in the broader manual.

400-4,000 CFMone published horizontal range
1-10 tonssame catalog family
0.249 kPapublished maximum external static

Those figures come from a Nailor horizontal fan-coil catalog and illustrate variation within that catalog family; labels such as “horizontal low-profile fan coil,” “horizontal high-performance fan coil” and “energy-efficient” still need a stated rating basis. A galvanized steel cabinet description and those figures are not Koven Air specifications or selection shortcuts. A Price Industries catalog reviewed for this manual lists units with 600 to 4,400 CFM airflow and 1.6 to 15 tons of capacity in a different product family. Therefore, a generic size can’t replace the selected operating point and its rating conditions.

Key takeaway

A ceiling-concealed horizontal fan coil is an overhead service system. Cabinet fit is only one acceptance input; interfaces and removal paths decide whether the installation remains operable.

Freeze the 12-Field Horizontal FCU Design-Basis Record Before Coordination

Freeze the 12-Field Horizontal FCU Design-Basis Record Before Coordination — Koven Air

A model number is too far along in the decision chain to carry the entire project. The design-basis record keeps three responsibilities separate: the designer’s calculation, the supplier’s selection and the installing trades’ field proof. “Freeze” means controlled for release: a later change requires a redline, named reviewer and a revised acceptance basis.

This isn’t the final asset record. NIBS COBie V3 separates product-type information from installed-component information. Serial number, final room, installation date and warranty start may not exist until implementation or handover, so they belong in the later packet.

12-Field Horizontal FCU Design-Basis Record
Field Decision owner Evidence at release Reject the record when
1. Zone load and mode Mechanical designer Sensible/total duty and heating duty at stated conditions The load basis or occupied mode is absent
2. Scheduled airflow Designer CFM or m³/h at the design mode Only a nominal unit size is shown
3. External static duty Airside designer Pa or in. w.g. with included components listed The value is “free delivery” or its boundary is unknown
4. Water design point Hydronic designer Entering/leaving temperature, flow and available pressure Temperature or flow basis conflicts with the coil selection
5. Circuit and coil Designer/supplier 2-pipe or 4-pipe duty, rows and connection schedule Plant sequence and terminal circuit disagree
6. Connection handing Supplier/coordinator View direction plus left/right pipe, drain and control-box locations “Left hand” is written without a viewing convention
7. Electrical supply Electrical designer Voltage, phase, frequency, protection and isolator location Supply and selected motor/control package do not match
8. Controls and points Controls designer Valve/fan sequence, sensor location, interlocks and point list A thermostat symbol is the only control definition
9. Sound and vibration Acoustic/mechanical designer Project criterion, rating basis, isolator and flexible-connection intent “Quiet” appears without a criterion or operating point
10. Cabinet and service route Architect/coordinator Selected-unit dimensions plus filter, blower, coil and valve access paths The cabinet fits but a service item cannot move
11. Condensate chain Mechanical/plumbing trades Pan outlet, trap or pump, fall, overflow response and termination The downstream route or operating-pressure basis is missing
12. Ventilation and filtration boundary Mechanical designer Recirculation, outdoor-air source, filter duty and room-pressure owner The unit label is assumed to prove fresh-air compliance

Worked record example: a designer might issue 5.0 kW sensible and 6.2 kW total cooling at 850 m³/h, with 7 °C entering and 12 °C leaving water, a documented external-static duty, 230 V single-phase power at 50 Hz, and measured 450 mm and 600 mm service-removal paths. Those figures only show what a complete unit record line looks like. They must be replaced with values from the project calculation, selected unit data and surveyed ceiling geometry. Thermal comfort and operating efficiency can’t be inferred from nominal capacity alone.

The design-basis record only refers to the commercial page when the project inputs are controlled. This keeps model and quotation content on the horizontal fan coil product page, while this guide keeps the coordination evidence.

Coordinate a Controlled Ceiling Baseline Before the Horizontal Unit Reaches Site

Coordinate a Controlled Ceiling Baseline Before the Horizontal Unit Reaches Site — Koven Air

A reflected ceiling plan can be used to show a unit rectangle and conceal a failure. The useful drawing also includes a finished grid, the structural suspension, a transition duct, water valves, the fall of the drain, an electrical isolator, a control box, light fixtures, sprinkler branches, and a service route tied to actual tasks.

The Price Industries access guidance identifies the blower/motor assembly, coils, filters and the electrical enclosure as separate access needs. Price does not give one universal access-opening size for every access need. That’s the correct boundary: prove the selected tasks against the selected unit and ceiling assembly. A removable ceiling tile may form part of the route if the opening, grid, fire rating and component movement all work; however, the drawing must show it because it can’t be assumed.

For example, a 600 mm × 600 mm ceiling module may yield only a 520 mm clear opening after allowing for its frame, while a blower module may need a 480 mm removal envelope plus a 40 mm insulated pipe crossing. A 150 mm valve-service path can disappear when a light fitting moves. The decision comes from the selected component envelope and the measured free path, not the nominal tile size.

Five-trade ceiling coordination check
Trade Show on the controlled baseline Field proof before change approval
Mechanical Cabinet, transitions, flexible connections, valve package and drain route Measured clearances and connection orientation
Architecture Ceiling grid, removable zone, finishes and fire-rating boundary Service items can pass without damaging permanent work
Structure Independent support points and allowable anchors Support location matches the approved load path
Electrical and controls Isolator, cable route, control box, sensor and actuator reach Safe access without removing unrelated services
Fire/plumbing coordination Sprinklers, sleeves, fire stopping, drain termination and overflow response No clash interrupts removal or gravity fall

For duct and plenum calculations, use the site’s duct and plenum checker. For early concealed-format screening, use the concealed FCU pre-specification checks. If site conditions change, mark the actual obstruction, revise the route and return the affected fields for approval. A controlled baseline is useful because it can change visibly.

Verify HVAC Air, Water, Drain and Control Interfaces Before Release

Verify HVAC Air, Water, Drain and Control Interfaces Before Release — Koven Air

The schedule may show access, but the release question is not “Does the schedule show capacity?” It is “Do the air, water, drain, electrical and control records describe the same installed operating mode?” One unresolved boundary can move the duty point or leave another trade holding an unowned task.

AAON defines external static pressure as the combined return-side and supply-side pressure reading on a manometer. Resistance from ducts and components affects airflow, sound and component load. That is why free-delivery airflow cannot serve as installed-airflow evidence.

14-interface release matrix
Interface Required input Evidence owner Consequence if open
1. Air volume Design CFM or m³/h by mode Designer Coil and fan selection cannot be checked
2. External static Pa or in. w.g. at the unit boundary Airside designer Installed airflow remains unknown
3. Filter duty Class, clean/dirty pressure basis and removal direction Designer/supplier Fan duty and access may both change
4. Supply path Duct, plenum, terminal and balancing-device losses Duct contractor/designer Room delivery and sound path are unproven
5. Return path Ducted return or ceiling-plenum boundary and leakage control Designer/architect Pressure relationship can depart from selection
6. Outdoor air Separate or integrated source, quantity and interlock Ventilation designer Room ventilation has no named system owner
7. Water temperature Entering/leaving values for cooling and heating Hydronic designer Published coil duty may not apply
8. Water flow and pressure Flow, available differential and coil/valve loss Hydronic designer Valve authority and balancing remain unresolved
9. Valve package Valve type, fail position, strainer, vent, drain and isolation Controls/hydronic teams Sequence and physical space can conflict
10. Condensate disposal Pan, trap or pump, fall, cleanout, overflow and termination Mechanical/plumbing teams Water damage route remains open
11. Insulation/vapor seal Cold pipe, valve, duct and cabinet coverage at joints Installer Surface condensation can occur outside the pan
12. Electrical protection Supply, local isolation, protection and earth Electrical team Start-up and safe service are blocked
13. Controls sequence Fan speeds, valve command, sensor, alarm and BMS points Controls team A powered fan may still operate incorrectly
14. Sound/vibration Rated condition, project criterion, isolation and transmission path Designer/installer Occupied-room performance is unbounded

Healthcare demonstrates the significance of ventilation requirements. When referencing fan-coil units, the CDC healthcare guidance assumes these units operate as recirculating systems and assigns outdoor air to a separate, filtered system. This example isn’t intended as a general code requirement, but rather as a suggestion to identify the outdoor air pathway for each project rather than assume it’s part of the fan coil unit.

The two-pipe vs four-pipe project check can be used to make the circuit selection. For sizing, use the hydronic load and water-side design guide. This keeps the interface-acceptance question in the foreground.

Use the 4-Witness Ceiling-Closure Proof Before Installation Is Hidden

Use the 4-Witness Ceiling-Closure Proof Before Installation Is Hidden — Koven Air

The “4-Witness Ceiling-Closure Proof” is a project control method and not a code or industry standard. This method places a visible hold point for four failure paths which become costly after being hidden. The project specifications and the installation instructions for the specified unit determine the acceptance criteria.

  1. Witness support — record the approved anchors, independent suspension, cabinet level and isolation arrangement.
  2. Witness drainage — run the specified wet or operating test and observe the pan, outlet, trap or pump, fall, overflow response and termination.
  3. Witness insulation — inspect vapor-sealed continuity at pipes, valves, ducts, fittings and cabinet interfaces before they disappear.
  4. Witness removability — demonstrate the selected filter, blower or motor, coil/valve and electrical service paths through the finished ceiling geometry.

Published evidence demonstrates that “drain connected” is not enough as proof. A Consulting-Specifying Engineer case study reports a trap with H = 0, a flooded pan, an approximate $2,000 correction and a four-inch unit lift. These values are applicable to that specific case. Your trap geometry stems from the unit pressure condition, the manufacturer’s instructions, the adopted code and the project design.

A connected drain does not account for every moisture path. The EPA illustrates condensation on an uninsulated air-conditioning duct and links cold-surface condensation to warm, humid air. Examine the vapor seal on cold pipes, valves and ducts separately from the drain pan and sloped drain test.

12 hold points in the closure record
Hold point Acceptable evidence Stop condition
Support points Approved anchors photographed and tagged Support bears on ceiling grid or unrelated service
Cabinet attitude Level/slope checked against selected IOM Pan cannot drain as intended
Duct support Duct is independently supported Transition loads the cabinet
Filter route Correct filter removed and reinserted Grid, cable or pipe blocks travel
Blower/motor route Service panel opens and removal envelope is marked Permanent work blocks the path
Valve/control reach Hands/tools reach isolation, vent, actuator and terminals Unrelated services require removal
Pan/outlet Clean pan and open outlet observed Debris or misalignment remains
Trap/pump route Approved geometry, cleanout and power/alarm where used Operating-pressure basis is unknown
Wet test Water clears without pan rise or joint leak Standing water or leakage appears
Overflow response Specified alarm, shutoff or safe discharge observed No response owner is named
Insulation continuity Joints, valves and penetrations are vapor sealed Cold metal is exposed
Record closure Photos, redlines, witnesses and exceptions are filed Evidence exists only in chat or memory

Commission the Fan Coil at the Installed Operating Point

Commission the Fan Coil at the Installed Operating Point — Koven Air

Having a motor run confirms the motor received a command. It doesn’t confirm design airflow, water response, drainage, the sequence of valve operation, accuracy of the sensors or the behavior of the occupied space. The U.S. Department of Energy defines commissioning as a planning, documenting, scheduling, testing, adjusting, verifying and training process.

The test population is project-specific. As a project-specification example rather than a universal rule, section 3.7.A.3 of a reviewed federal commissioning specification permits a sample defined by the commissioning agent for identical, non-life-safety or noncritical equipment. If such testing fails repeatedly, the sample expands to the remaining units. Do not use that example as a standard or default. Document whether the project requires every unit, a defined sample or a risk-based sequence, along with the escalation rule.

A useful test line might state 24 °C return air, 14 °C supply air, 7 °C entering water, 12 °C leaving water, 230 V supply, 1.8 A running current, 720 rpm fan speed, 50% control command, a 25 mm drain connection, a 20 mm water connection, 40 mm insulation and a 45 min condensate observation. The numbers are illustrative. Their value is that they pin every reading to one operating mode and time window, so a failed retest can’t be hidden by mixing conditions.

Eight-record installed operating-point packet
Record Instrument or observation Acceptance source Population
1. Fan and rotation Visual/tachometer/current as specified IOM and electrical schedule Each or sample per plan
2. Airflow Approved traverse, hood or balancing method Design air balance Defined test set
3. External static Manometer at documented return/supply points Selected fan curve and boundary Representative configurations
4. Water response Flow/balance record and entering/leaving temperatures Hydronic schedule Per circuit or plan
5. Condensate Operating or approved wet test; pump/alarm where fitted Drain design and IOM Population set by the commissioning plan; record pre-closure drain proof where required
6. Control sequence Command/feedback, valve action, fan stages and alarms Approved sequence and points list Defined functional sample
7. Sound/vibration Observation plus specified measurement method Project acoustic criterion Worst/typical locations
8. Exceptions/retest Issue log, correction and repeated measurement Commissioning plan Expand after failure as specified

CSE’s technical retro-commissioning guidance gives force to measurement points by requiring measurement of actual air and water flows, temperatures, and pressures, along with measurements of run times and inspection of ceiling void restrictions. Record the location of the probe, the operating mode, the instrument, and the acceptance reference. Without these four elements, the measurement is difficult to reconstruct, so “reliable” and “optimized performance” remain unsupported claims.

Build a Handover Packet That Keeps the Unit Serviceable

Build a Handover Packet That Keeps the Unit Serviceable — Koven Air

The design-basis record deliberately left a spot in the lifecycle record to be filled during handover. Product-type data records the selection and tells the owner what was selected. Component data tells the owner the specific asset, its location, and when its warranty clock began.

Eight handover records the facilities team can use
Record Minimum content Owner check
Asset identity Tag, model, serial and final space Matches cabinet and drawing
Approved product record Data sheet, options, connection handing and electrical package Superseded submittals removed
As-built ceiling record Coordinates, removable zone and service-route photos Accessible without guesswork
Water and air balance Final readings, locations, instruments and exceptions Values trace to acceptance basis
Controls record Sequence, points, setpoints, alarm logic and backups Actual operation matches document
Maintenance record Filter, pan, coil, motor/blower, valve and drain tasks Task frequency comes from approved documents
Warranty and spares Start date, contacts, exclusions and critical parts Site team can open a traceable case
Training and open issues Attendance, demonstrations, unresolved exceptions and owners No issue disappears at practical completion

Koven Air states that its service process starts with design and parameter verification, continues with pre-shipment testing and on-site installation and commissioning guidance, and includes lifetime technical guidance, warranty-period response and recurring training for contractors and engineers. These should be seen as first-party service assurances and the exact project description should be noted in the contract.

Troubleshoot from the Symptom to the Instrument

Troubleshoot from the Symptom to the Instrument — Koven Air

Finding the fault becomes costly when the assignment of symptoms to components occurs before measurement of operating conditions. Begin with the boundary that could create the symptom, then choose the first safe observation. The matrix below is meant to be a guide and shouldn’t be used as a substitute for the manufacturer’s instructions or a qualified technician.

Nine symptom types and the first evidence route
Symptom type First safe check Instrument/evidence Do not assume
Low room airflow Filter, grille, damper and fan command Airflow method plus return/supply static The motor is undersized
Low cooling capacity Airflow and water availability at the same mode Air/water temperatures, flow and valve command The coil is defective
Pan overflow Outlet, trap/pump, fall and operating pressure Visual level, wet test and pressure reference The drain only needs cleaning
Water below the unit Separate pan leakage from surface condensation Dry inspection, insulation/vapor-seal check and trace Every drip came through the pan
Gurgling/knocking drain Pressure sign, trap geometry and pump arrangement Manometer and observed drain behavior One trap detail fits every pressure condition
Short cycling Command, feedback, sensor location and valve response Trend log/current/time sequence The thermostat is the only cause
Unexpected noise Fan speed, static, panel, duct and structure paths Operating mode plus specified acoustic method Catalog sound equals room sound
Vibration Support, isolation, fan condition and flexible links Visual/approved vibration measurement A new isolator alone will fix the path
Wrong heating/cooling response Pipe circuit, valve position, sensor and plant mode Point-to-point sequence and water temperatures The unit received the intended water circuit
Do

  • Record the operating mode before measuring.
  • Use the instrument suited to the boundary.
  • Compare readings with the approved acceptance source.
  • Retest after one controlled change.
Don’t

  • Swap parts from a symptom alone.
  • Mix readings from different fan or valve modes.
  • Use forum advice as a universal dimension.
  • Close an issue without a repeatable record.

Survey a Horizontal Fan Coil Replacement Before Calling It Like-for-Like

Survey a Horizontal Fan Coil Replacement Before Calling It Like-for-Like — Koven Air

The replacement, even if it’s of nominally the same duty, may fail the tests of the ceiling route, pipe handing, drain elevation, electrical package, controls, and fan duty. Survey the installed condition prior to accepting a description of the purchase as “same as existing.”

The Boston Medical Center case reported by ACHR News included 84 fan coils: 68 vertical units, 10 horizontal units and 6 vertical hideaway units. The project also dealt with occupied-building phasing, sound, water pressure drop, special coil circuitry, piping and control extensions, warehousing and off-unit piping prefabrication. The main point of this case is that the challenges of field execution must be captured in the field replacement document.

Reuse, adapt or redesign decision
Survey field Reuse Adapt Redesign trigger
Duty point Measured demand and selected duty align Documented fan/coil change Load or system basis is unknown
Cabinet route Unit and service items pass Reversible finish work is approved Permanent structure blocks movement
Support Loads and points are verified Engineered support alteration Existing load path cannot be verified
Connections Handing and sizes align Approved spool/valve change Drain or isolation becomes inaccessible
Air system Measured resistance fits fan capability Documented duct/terminal change Required airflow cannot be proven
Electrical Supply/protection match Designed circuit modification Unsafe or unavailable supply
Controls Sequence and points map directly Documented interface conversion Required sequence cannot be implemented
Drainage Elevation and route are proven Approved trap/pump/route change No safe termination or overflow response
Occupied work Access and shutdown window fit Phased/prefabricated method agreed Safety or critical operation cannot be maintained

If the body style itself is the problem, compare other fan coil configurations rather than forcing a nominally similar horizontal cabinet or vertical cabinet into the existing constraint.

Send a Project-Ready Horizontal Fan Coil Unit Request

Send a Project-Ready Horizontal Fan Coil Unit Request — Koven Air

A supplier can verify more when the request carries the design basis and site boundary. Fill in the following fields in the quote request. “Recommended range” means the project’s verified value or allowed envelope, not a generic default.

RFQ checklist — copy these into your quote request:

Parameter Recommended range Why it matters How to verify
Air duty Project CFM or m³/h by mode Sets fan and coil operating point Load schedule and airside calculation
External static Project Pa or in. w.g. boundary Connects fan capability to installed resistance Duct/plenum/terminal loss schedule
Water duty Project °C, L/s or gpm and kPa Defines coil and valve selection Hydronic calculation and plant schedule
Pipe circuit 2-pipe or 4-pipe project arrangement Changes coils, valves and sequence System diagram and controls narrative
Electrical Project V/phase/Hz and protection Defines motor and control package Electrical schedule
Ceiling/service envelope Measured mm or in. paths Prevents a cabinet-only fit decision Coordinated drawing and removal demonstration
Drain/insulation Surveyed elevation, pressure condition and termination Controls pan drainage and surface condensation risk Drain sketch, IOM and closure witness
Controls/sound Approved points, sequence and acoustic criterion Defines occupied operation Controls matrix and project specification

Koven Air reports a 20,000 m² factory, 18 standardized production processes, 23 sheet-metal precision-machining processes, 400 manufacturing-process traceability points, 36 factory inspections and a 24-hour aging test. These are first-party manufacturing statements and can’t take the place of a project-specific submittal and witness plan.

Koven Air states that it was founded in 2007, began international brand development and exports in 2010, and has equipment operating in 35 countries. The stated application range includes hospitals, offices, industrial parks, agriculture, transportation, electronics, automobiles, semiconductors and data centers. Each scope is defined by its own specific needs for ventilation, sound, redundancy, cleanliness and service accessibility.

After the record is complete, use the KAFP selector as the model-selection handoff, or send the verified duty point to Koven Air.

Have a coordinated duty point and ceiling record?

Share the air, water, electrical, controls, drainage and service-envelope inputs for a project-specific review that checks the application, occupant needs, indoor conditions, heating and cooling duty, air pressure, sound levels, installation time, energy efficiency and contract alignment before configuration release.

Request Horizontal FCU Project Support →

Horizontal Fan Coil Unit FAQs

Horizontal Fan Coil Unit FAQs — Koven Air

What is a horizontal fan coil unit?

Answer

A horizontal fan coil unit is a room-side HVAC terminal arranged for horizontal mounting, often above a suspended ceiling. A fan moves air across a water coil for cooling, heating or both. The unit may connect to ducts or a plenum, but its name alone doesn’t define outdoor-air delivery, filtration, available external static, controls or service access.

How much does it cost to replace a fan coil unit?

Answer

A credible replacement price needs more than the old model number. The quote should include duty, cabinet and removal route, pipe handing, drain elevation, electrical supply, controls conversion, access reinstatement, testing, occupied-work constraints and disposal. Without those inputs, a low equipment price can hide field adaptation and ceiling work. Ask suppliers to separate equipment, accessories, installation support and commissioning scope.

Does a horizontal fan coil unit need ductwork?

Answer

Some horizontal fan coils serve supply and return ducts; others use a short supply connection with a ceiling-plenum return. The selected arrangement determines the fan’s external-static duty, leakage boundary, sound path, filter location and access plan. Confirm the project configuration, fan curve and pressure boundary rather than assuming every horizontal unit is fully ducted or suitable for the same duct resistance.

Why does a horizontal fan coil unit leak water?

Answer

Trace the source of the water first: the drain, pump, pan, a pipe joint or cold-surface condensation.

What measurements prove a fan coil unit has been commissioned?

Answer

The packet should identify the operating mode, airflow method, external-static test points, water temperatures and flow/balance evidence, valve and fan sequence, condensate response, electrical observations, sound/vibration check, instrument details, acceptance source and retest status. It should also name the drawing revision, selected model, room, test date, responsible witness, calibrated instruments, unresolved exception and required retest. The commissioning plan decides whether every unit or a defined sample receives each functional test. When a sampled unit fails, follow the project’s escalation rule rather than quietly treating the rest as accepted. A fan-start check by itself doesn’t establish installed performance.

Do horizontal fan coil units use refrigerant?

Answer

Many fan coil units use chilled or hot water at the terminal, while refrigerant remains in the central chiller or heat-pump circuit. Some products marketed with similar room-unit language are direct-expansion terminals that do carry refrigerant. Verify the coil medium, pipe schedule and plant connection on the selected product rather than relying on the family name.

References & Sources

A dependable handover does not claim that the unit works. It shows which operating mode was tested, what was measured, which acceptance source governed the result and how the ceiling still permits service.

Written by Karry for Koven Air Environment Technology Co., Ltd. This article includes first-party technology and factory statements provided by Koven Air. Project selection criteria must be checked against the selected equipment, local requirements and contract documents.

Factory Selection Support
Turn this guide into a usable HVAC RFQ package.

Share design conditions, airflow, temperature, humidity, process load, room use, and scope boundary. Koven Air can recommend a practical equipment route before quotation.

7equipment families ISO / GMPcleanroom review RFQscope comparison
Request Factory Quote Use Equipment Selector
What to prepare before quote
  • Use settingCommercial building, cleanroom, hospital, data center, process area, or retrofit.
  • Operating conditionsAirflow, load, temperature, humidity, static pressure, and duty hours.
  • ConstraintsFootprint, access, hygiene class, material, controls, documentation, and delivery boundary.

Final equipment selection depends on local codes, project drawings, and confirmed site conditions.