How to Specify and Verify an HTM-03-01 Hospital AHU

Updated August 2026

An HTM-03-01 Hospital AHU is an air-handling unit specified as part of a healthcare ventilation system governed by HTM 03-01. It cannot be accepted from a product label or filter grade alone. For healthcare projects in England, the ventilation brief must connect clinical use and room risk to airflow, pressure, distribution, controls, commissioning, independent validation, handover, and ongoing verification.

Direct answer: Use HTM 03-01 Part A to establish and validate the design for a new installation or major refurbishment, then use Part B to manage, inspect, and verify the operating system. Treat the AHU as one part of the installed ventilation system. Acceptance depends on measured performance and independent evidence from intake to discharge.

This is an England-focused decision guide, not a substitute for the current NHS documents, project risk assessment, or an Authorising Engineer (Ventilation). Scotland publishes SHTM 03-01 and Wales publishes WHTM 03-01. Core English guidance remains the 2021 Part A and Part B pair, while NETB 2023/01A is an addendum for portable and semi-fixed HEPA air-cleaning devices.

What this guide helps you decide

  • Which document and governance owner controls each lifecycle decision.
  • Which clinical inputs must be fixed before AHU selection begins.
  • How room function becomes measurable airflow, pressure, filtration, and control criteria.
  • Why commissioning and independent validation are separate acceptance stages.
  • Which records must survive handover so Part B verification has a reliable baseline.

What Does HTM 03-01 Cover, and How Do Part A and Part B Work Together?

What Does HTM 03-01 Cover, and How Do Part A and Part B Work Together?

HTM 03-01 is a Health Technical Memorandum for specialised ventilation in healthcare premises. For new installations and major refurbishments, Part A sets the design and validation standard. During operation, Part B governs maintenance, management, and performance verification. Neither health technical document turns a standalone AHU into a compliant installed system.

On its HTM 03-01 Part A document, NHS England identifies the 2021 edition as the design and validation reference for new installations and major refurbishments. The companion Part B governs operational management and performance verification. A live publication check still matters at the start of every project because an addendum can extend the evidence set without replacing the core edition.

Route the question before applying a requirement.
Question Primary source When it applies Decision owner
Concept, design, specification, installation, acceptance HTM 03-01 Part A New installation or major refurbishment in England Client team, VSG, designer, AE(V)
Operation, maintenance, routine testing, performance verification HTM 03-01 Part B Operating healthcare ventilation systems Healthcare organisation, VSG, AP(V), CP(V), AE(V)
Portable or semi-fixed HEPA air cleaner NETB 2023/01A Supplementary local air cleaning in healthcare spaces VSG and competent multidisciplinary team
Existing plant or minor change Part B plus project risk assessment Where Part A’s new/major-refurbishment scope is not triggered VSG with AE(V) advice
Non-acute healthcare setting NHS applicability statement plus local assessment Extent depends on treatment, patient condition, and intensity of use Those responsible for the facility
Scottish or Welsh project SHTM 03-01 or WHTM 03-01 Applicable devolved healthcare-estates regime Local healthcare body and appointed advisers

Is HTM 03-01 a legal requirement?

HTM 03-01 is NHS technical guidance, not a single Act of Parliament. Its language distinguishes requirements expressed as “must” from recommendations expressed as “should.” That doesn’t make it optional in practice: NHS projects, organisational policies, contracts, risk controls, and statutory duties can make compliance evidence central to acceptance. HSE separately notes the legal duty to provide sufficient fresh or purified air in enclosed workplaces. A safer question is: “What risk, contractual, policy, and legal basis supports any alternative?”

Paragraphs 4.10 and 4.11 require a proposed derogation or alternative strategy to receive scrutiny, written VSG agreement, and evidence that safety is no less. Evidence that a method has merely been used elsewhere isn’t enough. Record the reason, limits, approver, supporting evidence, and revalidation trigger.

Start With the Clinical Function, Not the AHU Catalogue

Start With the Clinical Function, Not the AHU Catalogue

The first specification is a clinical and operational brief, not a model number. The scope-and-governance framework above becomes usable only when the clinical team turns it into room-specific inputs. Define who uses the room, what the procedure releases, which direction contamination must move, how long the space operates, what happens on failure, and who owns the system after handover.

A room name alone can be ambiguous. “Isolation,” “treatment,” or “critical care” doesn’t automatically identify the applicable schedule row or pressure strategy. HSE’s general ventilation risk guidance also notes that adequacy depends on factors such as occupancy, floor space, and work activity. HTM 03-01 Part A still requires VSG and clinical stakeholders to agree the room classification, patient group, procedure, adjacent-space relationship, operating mode, and failure response before the mechanical schedule is frozen.

Clinical brief fields

Record the care setting; exact room function; patient and staff vulnerability; procedure and contaminant source; clean-to-less-clean airflow direction; adjacent rooms and door-opening pattern; occupancy and operating hours; required temperature, humidity, noise, and air distribution; normal, setback, purge, isolation, fire, and failure modes; local extract and make-up air; redundancy and power-loss response; monitoring and alarm recipients; cleaning method; maintenance access; verification method; governing jurisdiction; VSG decision; and every approved derogation.

Once those facts are agreed, product selection can begin. Koven Air’s HTM 03-01 compliant hospital AHU solution page covers equipment and the project-configuration route. This guide deliberately stops short of model comparison, prices, and quotations so the two pages serve different search intent.

Decision rule

If the clinical team cannot explain the contamination-control purpose and failure consequence, the AHU team cannot safely fill the missing fields with a generic hospital value.

Translate Room Risk Into Airflow, Pressure and Air-Distribution Logic

Translate Room Risk Into Airflow, Pressure and Air-Distribution Logic

Air changes per hour are one output, not the design method. Those clinical inputs become the boundary conditions for the airflow calculation. Under Part A paragraph 4.63, minimum supply is the greatest of five demands: fresh air, pressure or open-door need, thermal load, desired air-change rate, and make-up air for local extract. Each served room needs a scoped calculation.

Pressure is also relational. The negative room must be negative to a named adjacent space under defined door and plant conditions; a positive room must protect a named cleaner zone. Supply and extract quantities, fabric leakage, door movement, transfer paths, controls, and alarms work together. Fan duty alone doesn’t prove direction.

Examples from HTM 03-01 Part A room schedules; confirm the exact row and project conditions before use.
Room type Air change example Pressure example Other scheduled evidence
General ward 6 AC/h Schedule-dependent 35 dB(A), 18–28°C, SUP2
Single room 6 AC/h Neutral or negative 35 dB(A), 18–28°C
Clean utility 6 AC/h Positive SUP3, 45 dB(A), 18–22°C
Infectious-disease isolation 10 AC/h −5 Pa SUP2, 35 dB(A)
PPVL isolation bedroom 10 AC/h Lobby +10 Pa; bedroom neutral in the scheduled arrangement SUP2, 35 dB(A)
Neutropenic ward room 10 AC/h +10 Pa H12, 35 dB(A)
Critical care level 2 or 3 10 AC/h +10 Pa SUP1, 35 dB(A)
Bronchoscopy 10 AC/h −5 Pa 40 dB(A), 20–25°C, maximum 70% RH
Endoscopy 10 AC/h −5 Pa SUP2, 40 dB(A), 20–25°C
Operating recovery 15 AC/h 0 Pa SUP2, 45 dB(A), 18–25°C
Containment laboratory More than 20 AC/h Risk-specific containment cascade H14, 18–22°C
Post-mortem room 10 supply / 12 extract AC/h Negative SUP2, 45 dB(A), 18–22°C

The table is a navigation aid, not a substitute schedule. Values can depend on sub-room, lobby, supply-air category, distribution pattern, local extract, operational mode, and other notes in the source. Koven Air’s clinical room ventilation lookup helps identify candidate rows; verify each one against the official document and clinical brief.

Worked airflow example: calculate, then qualify

Suppose a 45 m² isolation room has a 3 m clear height. Its room volume is 135 m³. A schedule value of 10 AC/h corresponds to 1,350 m³/h. That is only the air-change candidate. Designers must still compare it with fresh-air demand, pressure/door-opening duty, cooling or heating load, and local-extract make-up. The largest governs under paragraph 4.63.

In this context, paragraph 4.68 calls for 5% for leakage and balancing plus 5% for uncertainty, a combined 10% design margin. Maximum duct leakage in the cited test is 3%. Applied illustratively to 1,350 m³/h, a 10% margin gives 1,485 m³/h, but this must not be mistaken for the final fan selection: system resistance, filter condition, control range, redundancy, heat recovery, sound, and actual scheduled notes remain unresolved.

For early arithmetic, Koven Air’s hospital AHU airflow sizing estimator can organize inputs. Treat its output as a preliminary check and preserve the approved design calculation as the acceptance record.

Air distribution determines whether the calculated air reaches the risk

Room-average AC/h can’t show what happens between a patient, clinician, contaminant source, supply terminal, door, and extract grille. Record the intended clean-to-less-clean path and inspect it under the real room layout. Tall equipment, privacy curtains, lights, pendants, storage, furniture, and open doors can redirect or short-circuit a theoretically adequate airflow.

Use a method suited to the question. Airflow measurements establish quantity; differential-pressure measurements test the relationship between named spaces; smoke visualization can show direction and local behavior; application-specific velocity tests address systems such as ultra-clean ventilation. Capture terminal positions, door states, control mode, occupancy simulation, instrument identity, calibration, and environmental conditions so the result can be repeated.

Pressure stability must be checked across the operating range, not only at one balancing point. Test clean and loaded filter states where the design requires them, normal and standby fan operation, relevant door movement, and the response to an alarm or loss of extract. A system that meets −5 Pa with every door closed but loses the intended direction during normal clinical movement has exposed a control or fabric problem, not merely a record-keeping issue.

Filtration, Drainage and Cleanability Must Be Verified as an Installed System

Filtration, Drainage and Cleanability Must Be Verified as an Installed System

Filter class describes media performance under a test framework; it does not prove the housing is sealed, the filter is seated, the access route is safe, the drain works, or room air reaches the filter effectively. Specify component, installation, test, maintenance, and disposal evidence together.

For filtration, Part A paragraph 4.30 gives an important correction to equipment-first thinking: almost all viable particles in a ventilated room originate from occupants rather than incoming air, so dilution is generally more important. ISO ePM1 ≥50% is cited for general areas; EPA/HEPA supply filtration is normally reserved for ultra-clean and designated clean rooms.

Special extract filtration is also risk based. Paragraph 9.61 says EPA/HEPA may be used where hazardous substances or organisms could be discharged, but the assessment must address need, installed validation, safe filter changing, and disposal. A general mortuary or post-mortem extract does not automatically require filtration.

Component-to-evidence matrix: nine claims that need installed proof.
Component claim Installation risk Acceptance evidence Part B check
Specified filter class Wrong grade or orientation installed Schedule, label, certificate, visual check Condition and replacement record
Low-leakage filter housing Bypass around frame or gasket Fit, seal, pressure, integrity test where required Seal and housing condition
Clean internal casing Debris retained after construction Pre-commission clean inspection and photographs At least three-monthly AHU visual inspection
Drain pan and fall Standing water or overflow Drainage test at operating pressure Tray, water colour, trap, and discharge inspection
Accessible wet section Coil or pan cannot be cleaned Measured access envelope and removal demonstration Safe recurring cleaning access
Filter-pressure monitoring Blocked filter goes unnoticed Calibrated reading, alarm, BMS point test Trend and alarm-function review
Isolation damper Air reverses on shutdown Failure-mode and spring-return functional test Operation and leakage-condition check
Portable HEPA device Short-circuit airflow or blocked discharge Room placement, CADR basis, airflow and noise validation Annual performance, alarm, filter, and safety checks
Safe filter change Contaminated dust released in clinical area Method statement, PPE, bagging, disposal route Training and waste records

NETB 2023/01A does not overturn the risk-based message. It addresses local portable and semi-fixed HEPA devices, recommends H13 or H14 performance for healthcare applications, and warns that air cleaners must not be used as a reason to reduce fresh-air ventilation. Room performance depends on airflow rate, device placement, room layout, background ventilation, operation, and maintenance, not filter efficiency alone.

In a healthcare environment, a stringent air-quality target still needs a defined engineering purpose. Healthcare facilities and healthcare buildings contain different clinical risks, room geometries, occupants, and operating patterns; NHS Improvement-era labels or older project documents should never replace the current source set and locally approved risk assessment.

Cleanroom projects can introduce a different classification and validation context. The cleanroom HVAC validation guide explains that adjacent topic; it should not be used to replace the healthcare room schedule.

Integrate the AHU With Plant Space, Controls, Resilience and Maintenance Access

Integrate the AHU With Plant Space, Controls, Resilience and Maintenance Access

Even a suitable AHU can fail its clinical purpose when the plantroom, duct system, controls, drainage, power, or maintenance route is wrong. The same installed-system logic that governs filtration and drainage also applies to the surrounding plant and controls. Integration review must prove safe installation, testing, isolation, cleaning, repair, and replacement under the agreed operating and failure strategy.

Start at the air intake and finish at the discharge, as the validator will. HSE’s mechanical-ventilation guidance points to the full duct-and-fan route and the need for an engineer to check whether a system provides adequate ventilation. The healthcare-specific whole-system validation route in HTM 03-01 Part A then means checking contamination sources around the intake, weather protection, access, fan and filter removal, coil withdrawal, drain gradients, trap pressure, duct cleanability, measurement stations, fire interfaces, terminal distribution, exhaust discharge, and the route for safe filter disposal.

Part A paragraph 9.12 calls for airflow nature and direction to be clearly marked on ducts. Paragraph 9.19 specifies motorised, spring-return, low-leakage BS EN 1751 class 3 isolation dampers at AHU connections, closing on failure or shutdown to prevent reversal. These details turn a drawing arrow into a testable failure state.

Controls need an evidence owner

For every alarm and mode, name the initiating condition, sensor, setpoint or threshold, delay, commanded response, displayed message, recipient, escalation path, and reset authority. Test normal, setback, fire, purge, isolation, loss of airflow, dirty filter, fan failure, sensor failure, power restoration, and duty/standby changeover where applicable.

Measurement facilities should be designed in, not improvised later. Accessible duct test points, calibrated instruments, reliable differential-pressure taps, room reference points, and BMS trends make annual verification repeatable. CIBSE’s healthcare measurement discussion reinforces the practical point: inaccessible or poorly located sensors can make a compliant intent unprovable.

Resilience is a clinical consequence decision

Don’t apply redundancy as a generic badge. Define the consequence and permitted duration of losing supply, extract, pressure cascade, temperature, humidity, or monitoring. Then decide whether the response needs standby fans, dual power, automatic changeover, local indication, remote alarm, protected controls, or an operational shutdown plan. Record what the system can maintain during maintenance, not only during an electrical fault.

Existing plant also needs an honest suitability check. Retention under Part A is conditional and uses a 10-year age threshold alongside the ability to achieve full compliance. Midlife refurbishment under Part B often occurs at about 10 years, with the system taken out of use, inspected, cleaned, assessed for corrosion, considered for controls upgrades, and validated before return. Age alone neither condemns nor validates the plant.

Commissioning Proves Performance; Independent Validation Proves Fitness for Purpose

Commissioning Proves Performance; Independent Validation Proves Fitness for Purpose

Commissioning brings the installed system to its specified operating condition and records performance. With integration resolved, commissioning can test the installed operating state. Independent validation asks whether the whole system is fit for its agreed healthcare purpose and whether the client should accept it. The second cannot be replaced by the contractor’s commissioning sheet or an AHU factory test.

Commissioning guidance in paragraph 11.3 describes the process as essential and expects provision at the design stage, referring to relevant CIBSE codes and BSRIA BG49. Paragraph 11.27 says construction should be complete before dynamic commissioning: rubbish removed, floors cleaned, panels and access complete, and ceilings finished. Otherwise dust, missing fabric, open panels, and unfinished doors can invalidate the measured state.

Paragraphs 12.1 to 12.4 then establish independent validation before client acceptance for new and refurbished systems. The client appoints a suitably qualified engineer—an AE(V) or similarly qualified person—who is independent of the designers, contractors, suppliers, installers, commissioners, and later operators. Validation covers the entire system from intake to discharge.

“All new and refurbished ventilation systems should be independently validated prior to acceptance by the client.”

Commissioning and validation use overlapping measurements for different decisions.
Aspect Commissioning Independent validation
Purpose Set up and demonstrate specified operation Advise the client whether the system is fit for purpose and acceptable
Independence Typically part of delivery Client-appointed and independent of delivery and operation parties
Boundary Systems and functions in the commissioning plan Whole ventilation system from intake to discharge
Inputs Approved design, equipment data, sequence, test plan Clinical intent, approved design, commissioning evidence, inspections, witnessed tests
Output Commissioning manual, readings, settings, deficiencies Full report and clear statement on achievement of the agreed design standard
Acceptance effect Provides essential evidence Supports the client’s acceptance decision

Build a witnessable test sequence

  1. Confirm readiness: construction, cleaning, access, labels, doors, ceilings, controls, utilities, and calibrated instruments are complete.
  2. Inspect the system: trace intake, AHU sections, ducts, dampers, terminals, rooms, extracts, and discharge against drawings.
  3. Prove functions. Test modes, interlocks, failure actions, alarms, standby operation, BMS points, and safe reset.
  4. Measure performance. Record main and branch airflows, room supply/extract, air-change rate where applicable, pressure relationships, temperature, humidity, noise, and application-specific velocity.
  5. Resolve deviations. Link each defect to an owner, corrective action, retest, and acceptance status.
  6. Issue the conclusion. Paragraph 12.32 requires a full report and a clear statement on whether the agreed design standard was achieved.

Handover Creates the Evidence Baseline for Part B Governance

Handover Creates the Evidence Baseline for Part B Governance

Handover is the transfer of a measurable operating baseline, not a box of manuals. The validation conclusion then becomes the starting point for operation, rather than a one-off acceptance record. Operations teams need the design, installation, measurements, accepted settings, outstanding conditions, and recurring-task owners in one controlled record.

Part A paragraph 11.11 requires commissioning information to be assembled in the commissioning manual and handed over with as-fitted drawings. Paragraph 13.3 expands the information baseline, including drawings, schematics, and room design-versus-actual airflow data. Paragraph 13.36 requires training for end users and for those who operate and maintain the system.

Minimum handover evidence map.
Evidence package What it should resolve Part B use
Clinical and design brief Room classification, risks, required conditions, failure response Governance and change control
As-fitted drawings and schematics Actual system boundary, components, flow direction, test points Safe maintenance and fault isolation
Equipment and filter schedules Installed identity, duty, grade, spares Inspection and replacement planning
Controls narrative and points list Modes, setpoints, alarms, interlocks, reset authority Functional testing and alarm response
Commissioning manual Settings, balancing, readings, witnessed results Baseline for later comparison
Independent validation report Fitness-for-purpose conclusion and unresolved conditions Acceptance and risk register
O&M and safe work procedures Cleaning, filter change, isolation, disposal, calibration Competent maintenance delivery
Training and competence records Who was trained for which task and system Appointment and refresher decisions
Derogations and change history Approved variance, evidence, limits, review trigger Revalidation and future modification control

Governance under Part B assigns roles rather than leaving “facilities” as an unnamed owner. A healthcare organisation establishes a Ventilation Safety Group linked to board-level governance. AE(V) provides independent audit and advice; AP(V) implements the safety policy in practice; and CP(V) performs maintenance and periodic testing within competence and appointment limits.

Record retention is measurable. Paragraph 1.44 calls for at least five years for ordinary ventilation records and 25 years for manufacturing-pharmacy records. Paragraph 5.46 also sets at least five years for maintenance records. Retention needs a named repository, document owner, version method, access control, backup, and link to the system inventory.

Inspection, Verification, Failure Response and Revalidation Under Part B

Inspection, Verification, Failure Response and Revalidation Under Part B

Inspection under Part B separates frequent observation from detailed measurement. All ventilation systems receive at least a simple annual visual inspection. Critical healthcare ventilation is visually inspected quarterly and performance-verified annually. AHUs receive internal and external visual inspection at least every three months. These intervals don’t remove the need for additional risk-based checks.

Part B paragraph 1.47 makes the distinction explicit: visual inspection checks apparent condition; annual verification measures and records performance. Paragraphs 5.6 and 5.7 add AHU condition, connections, controls, the ability to maintain conditions, and drainage cleanliness and operation. Tray cleanliness and water colour can expose a fault.

Part B operating cadence and evidence.
Activity Minimum or typical interval Evidence Escalation trigger
All-system simple visual inspection At least annually Condition record and defects Damage, contamination, alarm, changed use
Critical healthcare ventilation visual inspection Quarterly System and room-condition checklist Loss of required condition or visible deterioration
Critical healthcare performance verification Annually Measured airflow, pressure, environment, controls, report Outside acceptance limit or unexplained drift
AHU internal/external visual inspection At least every 3 months Casing, components, connections, controls, cleanliness Corrosion, water, dirt, seal or control fault
Midlife refurbishment review Typically around 10 years Out-of-use inspection, clean, corrosion and controls review Condition, obsolescence, compliance gap
Revalidation After relevant refurbishment/change or failed condition New validation conclusion Change could affect fitness for purpose

What happens when critical ventilation fails verification?

Paragraph 4.34 says a failed critical system shouldn’t be returned to service as though nothing happened. It requires the duty manager to be informed, with reporting to the user department, infection prevention and control, and the AP(V). Next, the organisation controls the clinical risk, investigates the cause, records decisions, repairs or modifies the system, and repeats the required evidence.

After refurbishment, paragraph 4.35 requires full validation before reuse. A passed component test or restored fan status isn’t necessarily enough: the acceptance question concerns the served clinical environment and whole-system function. Define who can declare the system unavailable, who can accept temporary operational controls, and who can authorize return to clinical use.

The Clinical Risk-to-Evidence Chain: A Five-Gate Acceptance Check

The Clinical Risk-to-Evidence Chain: A Five-Gate Acceptance Check

Koven Air’s Clinical Risk-to-Evidence Chain is a decision framework derived from the lifecycle in HTM 03-01 Part A and Part B; it isn’t a replacement standard. A project advances only when each gate has an accountable owner, an approved input, measurable evidence, and a clear disposition for open items. Failure at one gate remains visible.

Five gates from clinical purpose to governed operation.
Gate Question Minimum evidence Do not pass when
1. Clinical purpose What harm is ventilation controlling, for whom, and in which operating modes? Approved room classification, risk assessment, adjacency and failure consequence Room name substitutes for an agreed clinical brief
2. Measurable design How does the purpose become airflow, pressure, distribution, environment, controls and resilience? Calculations, schedules, diagrams, mode table, derogations A generic ACH or filter value fills an unapproved gap
3. Installed proof Was the complete system installed, cleaned, set up and functionally tested? Inspection, commissioning manual, calibrated readings, alarm tests, defect closure Factory data is standing in for site evidence
4. Independent acceptance Does an independent client-appointed validator find the whole system fit for purpose? Validation report and explicit achieved/not-achieved conclusion Independence, system boundary, or conclusion is unclear
5. Governed operation Can the organisation preserve, verify and recover the accepted condition? Named VSG/AP(V)/CP(V)/AE(V), inventory, logbook, training, intervals, failure plan Handover lacks a baseline, owner, interval or failure response

This framework prevents three common handoff errors. First, it stops a product certificate from being stretched into system acceptance. Second, it stops successful commissioning from being labelled independent validation. Third, it stops a passed validation from being treated as permanent: ongoing governance must maintain and periodically re-prove the accepted condition.

Use the gates during bid comparison

A bid comparison should score evidence against the same approved brief. Ask every bidder to state assumptions, exclusions, calculation conditions, filter stages, casing and leakage basis, fan operating points, spare capacity, sound basis, control interface, access envelope, drainage arrangement, commissioning scope, validation support, handover records, and training. Separate “included,” “by others,” and “not demonstrated.”

Don’t award an apparent technical advantage that exists only because one proposal assumed a lower airflow, cleaner filter, smaller external static pressure, easier sound criterion, or narrower controls scope. Normalize the inputs first. When an alternative strategy is proposed, require the safety evidence, limits, VSG route, and future verification method before treating it as equal.

This result is a procurement handoff without turning the guide into a supplier-comparison page. The clinical brief and acceptance gates define what evidence a product solution must provide; the commercial page can then present configuration, drawings, selection data, and quotation against those frozen inputs.

Acceptance sentence to require:

“For the named clinical rooms, operating modes, boundaries, approved derogations, and test conditions, the documented evidence shows whether the agreed design standard was achieved; all exceptions, owners, restrictions, and revalidation triggers are listed.”

Frequently Asked Questions

What does HTM 03-01 cover?

HTM 03-01 covers specialised ventilation for healthcare premises, linking Part A design and acceptance requirements with Part B management, maintenance, inspection, and performance verification after handover.
For England, new installations and major refurbishments use Part A for concept, design, specification, installation, commissioning and independent validation. During operation, Part B addresses management, maintenance and performance verification. Applicability outside acute care requires assessment of the treatment, patient condition and intensity of use. Current evidence can also include NHS Estates Technical Bulletins: NETB 2023/01A is an addendum for portable and semi-fixed HEPA devices. Scotland and Wales publish SHTM and WHTM versions, so a project team should confirm its jurisdiction, project type, care setting, applicable addenda and local governance route before copying a requirement into a brief.

Is an HTM 03-01 compliant AHU enough for compliance?

No. AHU construction and component selection are only part of the evidence; the installed ventilation system must also meet the agreed clinical purpose through commissioning and independent validation.
Acceptance also depends on intake and discharge location, ductwork, air distribution, room leakage, pressure relationships, controls, drainage, access, commissioning, independent validation, records, and governance. Use a product claim as one input to the design evidence chain, never as the final conclusion. A factory test can’t reproduce the installed duct resistance, room fabric, terminal arrangement, control sequence, or clinical operating conditions.

Does every hospital room require HEPA filtration?

No. HTM 03-01 uses room function and clinical risk to determine filtration; HEPA is generally reserved for defined applications, and portable devices cannot replace required fresh-air ventilation.
Paragraph 4.30 notes that occupants generate almost all viable particles in ventilated rooms and that dilution is normally more important. EPA/HEPA supply filters are generally limited to ultra-clean and designated clean rooms. Special extract filtration needs a risk assessment, installed validation, and safe change/disposal plan. Portable HEPA devices are covered by NETB 2023/01A and mustn’t be used to justify reducing required fresh-air ventilation.

What is the difference between commissioning and validation?

Commissioning sets up and demonstrates the installed system’s specified operation, while independent validation gives the client an impartial judgement on whole-system fitness for the agreed healthcare purpose.
A client-appointed validator is independent of designers, contractors, suppliers, installers, commissioners, and operators. Validation reviews the whole system from intake to discharge and ends with a clear statement on whether the agreed design standard was achieved.

How often is critical healthcare ventilation verified?

Part B calls for quarterly visual inspection and annual performance measurement and verification of critical healthcare ventilation, with added checks or revalidation when risk, condition, alarms, changes, or failure justify them.
AHUs also receive visual inspection at least every three months, while all systems receive at least a simple annual visual inspection. Risk, condition, alarms, changed room use, maintenance, or failure can justify additional checks or revalidation.

How long should hospital ventilation records be kept?

Part B sets a minimum of five years for ordinary ventilation records and 25 years for manufacturing-pharmacy records, while project teams should retain the accepted baseline and change history together.
Keep the accepted baseline, maintenance, verification, defects, changes and revalidation evidence together.

Turn the approved brief into an AHU review

When the clinical purpose, room schedule, system boundary, failure modes, test method, and evidence owners are defined, move to project-specific equipment evaluation.

Discuss Your Hospital AHU Brief

How this guide was prepared

Preparation drew from the current NHS England publication page, locally reviewed Part A and Part B PDFs, the NETB 2023/01A HEPA addendum, HSE context, and implementation material from IHEEM and CIBSE. Numerical examples retain their source-room scope. No project outcome, company capacity, or named expert endorsement was invented. Learn more about Koven Air.

Factory Selection Support
Turn this guide into a usable HVAC RFQ package.

Share design conditions, airflow, temperature, humidity, process load, room use, and scope boundary. Koven Air can recommend a practical equipment route before quotation.

7equipment families ISO / GMPcleanroom review RFQscope comparison
Request Factory Quote Use Equipment Selector
What to prepare before quote
  • Use settingCommercial building, cleanroom, hospital, data center, process area, or retrofit.
  • Operating conditionsAirflow, load, temperature, humidity, static pressure, and duty hours.
  • ConstraintsFootprint, access, hygiene class, material, controls, documentation, and delivery boundary.

Final equipment selection depends on local codes, project drawings, and confirmed site conditions.